Procuring steel in major projects
On 2nd November emergency government measures to address the fledgling UK steel industry were introduced, requiring that main contractors reveal the sources of their steelwork when bidding for major projects.
Such measures come in the wake of the Tata Steel plant closure in Scunthorpe and in response to concerns that projects such as HS2 will incorporate large quantities of cheap steel imported from China, thereby casting doubt on the long-term viability of UK steelwork fabricators and suppliers.
Clients like HS2, Network Rail and Highways England will require that contractors set out details of how and from which supplier their steel will be sourced. Public works contracts will stipulate that if a supplier has not been selected at contract award, the main contractors and relevant steelwork firms must advertise openly for steel supply opportunities.
The ‘Procurement Policy Note: Procuring steel in major projects’ guidance is intended to support UK steel suppliers in competing for government contracts, and applies to all infrastructure, construction or any major procurement project with a total steelwork content valued at over £10m.
The key actions introduced by the guidance are:
- Signaling future pipelines of demand for steel: The aim is to give suppliers greater confidence to plan for the future, and support a more strategic approach to the management of supply markets.
- Effective pre-procurement engagement: It is thought that this will help to stimulate increased competition and give potential suppliers a better understanding of the nature of the requirement, intended approach, committed volumes and scale.
- Supply chain transparency and advertising supply chain opportunities.
- Assessing potential suppliers in the supply chain at selection stage: The aim is to ensure that all key subcontractors responsible for the delivery of steel are compliant with the relevant health and safety and employment legislation of the country in which they are based.
- Ensuring value for money is calculated on a whole-life cost basis: The award of contracts should be on the basis of the most economically advantageous tender.
- Evaluating social and environmental benefits and impacts.
- Managing contractors’ obligations.
Paymaster General Matthew Hancock said: “By asking procurers on major UK projects to consider social and environmental impacts, we are building a Britain that is happier, healthier and better off.
"We will always strive to get the best value for money for taxpayers and we are going to do so in a way that strengthens our economy and bolsters the long-term prosperity of people across the country.
I don’t want contracts going abroad if the best bid is a British bid with all the social and economic benefits that brings.”
You can read the government's guidance report here.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.